INP-WealthPk

11 NHA highway projects consume Rs178bn with over Rs111bn needed for completion

October 16, 2026

By Abdul Ghani

Eleven major highway projects undertaken by the National Highway Authority (NHA) are at varying stages of completion, with cumulative expenditure reaching Rs178.38 billion by June 2026.

According to a document available with Wealth Pakistan, the government earmarked around Rs23.62 billion under PSDP 2026-27 for the projects, while releases during the first quarter of the fiscal year 2026-27 stood at approximately Rs4.96 billion.

The projects cover important road links across the country and are at varying stages of physical completion, ranging from 21% to 75%. This indicates that while several schemes are approaching their final stages, others categorized under the near-completion portfolio still require substantial construction work.

Among the projects, land acquisition, affected-property compensation, and relocation of utilities for construction of the 959Km Karachi-Lahore Motorway (KLM) carry the largest cumulative expenditure of around Rs45.319 billion up to June 2026. Its physical progress is 68%, with Rs800 million allocated for FY2026-27.

The Shandur-Gilgit Road project, measuring 216 kilometres, is another major scheme in the portfolio. Cumulative expenditure up to June 2026 stands at about Rs42.21 billion, while its FY2026-27 allocation is Rs1 billion. The document records varying progress across its packages, with some sections considerably more advanced than others.

Another major scheme concerns the Hoshab-Awaran-Khuzdar section of M-8, where two sections are under construction. The Hoshab-Awaran-Naal section carries cumulative expenditure of approximately Rs23.26 billion, with an allocation of Rs3 billion during FY2026-27. Package-wise progress ranges from roughly 45% to 60%.

The Hoshab-Awaran section, meanwhile, has reached a cumulative expenditure of about Rs10.23 billion, with an additional Rs3.5 billion allocated for the and FY2026-27 fiscal year. Physical progress across its packages ranges from around 62% to 66%.

The document also lists an additional carriageway project (Shikarpur-Rajanpur section) on the Indus Highway (N-55) among the near-completion projects. Cumulative spending reached around Rs31.34 billion through June 2026, while Rs5 billion was allocated for FY2026-27. Progress varies substantially among its four lots, from around 22% to 94%.

Other projects in the portfolio include land acquisition and compensation for the Rajanpur-DG Khan section of N-55, improvement and widening of the Chitral-Booni-Mastuj-Shandur Road, construction of a flyover at the junction of N-5 and N-65 in Sukkur, extension of the Mansehra Highway from GT Road (N-5) to Motorway (M-1), construction of a link highway connecting the Lahore-Sialkot Motorway with Narowal through the Narang Mandi area, and rehabilitation and upgrading of the Pezu-Tank Road.

According to data, these 11 projects have a combined throw-forward requirement of around Rs111.51 billion as of July 2026.

During the first quarter of FY2026-27, approximately Rs4.96 billion was released against the near-completion portfolio. Utilisation was recorded at roughly Rs3.49 billion, while outstanding liabilities stood at approximately Rs16.46 billion.

Credit: INP-WealthPk