i INP-WEALTHPK

Peshawar, Charsadda gas supply schemes make steady headwayBreaking

September 24, 2026

By Ayesha Saba

The Sui Northern Gas Pipelines Limited (SNGPL) infrastructure in Peshawar and Charsadda is making steady progress, with approved schemes in Peshawar reaching 60% physical progress and those in Charsadda 51%.

According to a document available with Wealth Pakistan, the summary covers gas schemes approved for Peshawar and Charsadda districts during FY2013-2026.

In Peshawar, a total of 10 schemes covering 912.69 kilometres have been approved at a total cost of Rs2,731.10 million. Physical progress across these schemes stands at 543.33 kilometres, or 60%.

Five of 10 schemes in Peshawar have been completed, covering a total length of 216.63 kilometres and carrying a total cost of Rs619.31 million. The document records their physical progress at 100%, covering 201.68 kilometres.

Another five schemes in Peshawar remain ongoing, covering 696.06 kilometres at a total cost of Rs2,111.79 million. Physical progress on the ongoing schemes stands at 341.65 kilometres, or 49%.

For Peshawar as a whole, the total sanctioned amount stands at Rs1,898.60 million, covering a network of 605.19 kilometres. Government funds released are recorded at Rs586.51 million.

In Charsadda, nine gas supply schemes covering a total length of 886.22 kilometres have been approved at an overall cost of Rs2,675.70 million.

Physical progress across the Charsadda schemes has reached 454.37 kilometres, equivalent to 51%.

Two schemes in the district have already been completed, covering 26.62 kilometres at a total cost of Rs75.63 million. Their physical progress is recorded at 100%, covering 22.33 kilometres.

Seven schemes remain ongoing in Charsadda, covering 859.59 kilometres at a total cost of Rs2,600.07 million. Physical progress on these schemes has reached 432.04 kilometres, or 50%.

The sanctioned amount for Charsadda stands at Rs2,621.90 million, covering a network of 715.74 kilometres, while government funds released are recorded at Rs179.55 million.

The document also shows a balance network of 292.95 kilometres in Peshawar and 166.20 kilometres in Charsadda, as work on the remaining schemes continues.

Credit: INP-WealthPk